20 °F Ocean City, US
December 22, 2024

Ocean City’s northend beach replenishment project nearly complete

OCEAN CITY – At the end of last week, Ocean City’s beach replenishment project had reached the 11th Street beach and this week should be close to finishing at 14th Street.

This is the 10th time the U.S. Army Corps of Engineers has replenished the sand in the north end of the resort since the beginning of a 50-year agreement. The federal and state governments pick up about 90 percent of the cost of the project.

The north end gets refilled every three years under the agreement. The south end, part of a different agreement, is scheduled for a fill later this year.

This latest project, which stretched from the north end to 14th Street, was part of a $21.5 million contract to put some 1.2 million cubic yards of sand on the beaches.

Work began in the late fall when the pipe from the dredge landed on the Morningside Road beach, started to pump sand from the dredge area off the coast to the north and then the fill proceeded southward in the ensuing weeks. 

The beach was closed in 1,000-foot sections as the work progressed. At the end of last week, the work had already filled the sand under the pilings of the Ocean City Music Pier and the beaches beyond Moorlyn Terrace. Bulldozers worked on the beach and in the surf moving the sand pumped in to rebuild both the beaches and the dunes that had been devoured by storms.

In his letter to the city posted Friday, Mayor Jay Gillian predicted work would be complete within days and then Great Lakes Dredge and Dock Co., the contractor, would return to touch up the beaches from Fourth Street north.

Related articles

Most parents are OK with students’ return to school

Ocean City district survey says health, safety priorities, but so is the education By DAVID NAHAN/Sentinel staff When the Ocean City School District polled parents earlier this month, it found most are comfortable with their students returning to school, but they remain worried about their children’s physical health and safety and emotional needs. The majority […]

Seaville hotel proposal gets Zoning Board approval

SEAVILLE — The plan to build a hotel and restaurant on Route 9 in Seaville has moved one giant step forward with the Zoning Board’s 6-1 approval of multiple variances. The proposal, which the board initially tabled, was presented again Aug. 1 following amendments. Applicant John Federico’s initial plan called for 24 apartments and 108 […]

Leave a Reply

Your email address will not be published. Required fields are marked *